November 12, 2026·47 min read

MARA Holdings (MARA), Financial Analysis

Insights derived from analysing SEC filings. Independent analysis, not a publication of the SEC.

Revenue Q3 2026
$164m
(34.9%) year on year (Q3 2025 $252m)
Total costs and expenses Q3 2026
($12m)
Negative because a $422m bitcoin gain is netted in; $410m before the gain (Q3 2025 $439m)
Operating margin Q3 2026
n/m
Operating income $177m exceeds revenue because of the bitcoin gain; (149.4%) excluding it (Q3 2025 18.9%)
Key findings
  • Mining output rose, revenue per coin fell. Q3 2026 revenue $164.2m, (34.9%): bitcoin mining $159.0m, other $4.8m, hosting nil since Q1 2026. Production 2,247 BTC (+4.8%), 6,916 in 9M 2026; average price of BTC mined $71,688, (37.4%); energized hashrate 71.2 EH/s on about 1.9 GW.
  • Bitcoin marks drive earnings. Fair value gain on digital assets, incl. loaned and pledged bitcoin, $885.3m in Q3 2026 and a loss of ($476.3m) in 9M 2026; net income and adjusted EBITDA include these swings. Q3 net income attributable to MARA $634.4m ($632.1m incl. noncontrolling interests, which carried a $2.3m loss), diluted EPS $1.28; operating income $176.5m, or ($245.3m) excluding the $421.9m gain on digital assets inside it (computed).
  • Costs per coin stayed near $40,000. Purchased energy cost $39,674 per BTC at owned sites (payments to power providers divided by BTC produced at owned sites, as filed) against $39,235; energy cost 54.6% of owned mining revenue against 34.3%. Gross profit, computed as revenue less energy, hosting, maintenance and depreciation, ($127.7m).
  • The treasury turned to selling. 34,012 BTC at 30 Sep 2026 ($2.84bn at $83,556; cost $2.70bn): 14,752 unrestricted, 1,408 loaned, 17,852 pledged. After 30 Sep 2026 MARA sold 13,597 BTC for about $1.1bn and repaid $750m of bitcoin backed loans in full (subsequent events, 10-Q of 9 Nov 2026); 26,984 BTC were sold in 9M 2026.
  • Debt and funding: convertible notes $2.30bn principal, with holder puts in Jun 2027 ($291.6m) and Dec 2027 ($632.5m); at the market sales $46.5m gross in Jul 2026, about $1.5bn of capacity left; $500m share buyback authorized on 9 Nov 2026. AI and HPC: Exaion $79m four year GPU contract; Long Ridge approved by FERC on 4 Nov 2026, closing pending at 12 Nov 2026; Matagorda rights to up to 2 GW; Starwood joint ventures with no leases signed at 9 Nov 2026.
  • Shares closed at $7.66 on 11 Nov 2026, 53.4% below the 52 week high; market value 1.04 times bitcoin fair value at 30 Sep 2026 and enterprise value less bitcoin 3.1 times TTM revenue (computed). Three year model on that EV/sales basis: base $8.47, best $17.29, worst $3.29.

Figures are read from the Forms 10-K for FY2023 (amended), FY2024 and FY2025, the Forms 10-Q for Q1 2025 to Q3 2026, the Forms 8-K with all their exhibits (13 filings from 12 Nov 2025 to 12 Nov 2026), incl. the quarterly shareholder letters (Ex 99.1) with the CFO commentary, the Long Ridge, Starwood and Matagorda filings, the Form 8-K Item 5.07 vote results and Forms 4 of the last twelve months, together with the latest Forms 10-Q of Riot Platforms, CleanSpark, Cipher Digital, Core Scientific, IREN, Hut 8 and Strategy. Accession numbers for every filing used appear in the Sources appendix. Gross profit, capital expenditure and the valuation ratios are computed for this report from filed lines.

1 Revenue & Business Model

  • Storyline: MARA mines bitcoin, has moved from holding to selling part of its bitcoin, and is building a power and AI business on its sites. Chapters 2 to 4 cover the three drivers: bitcoin mining, the bitcoin treasury, and AI, HPC and power.
  • Operations: 19 data centers at 30 Sep 2026 (18 in the FY2025 Form 10-K) with about 1.9 GW of total energy capacity; owned sites about 70% of operating capacity and hosted sites 536 MW and 29.2 EH/s at 31 Dec 2025; about 490,000 rigs and 266 employees (10-K FY2025).
  • Revenue lines, Q3 2026: bitcoin mining $159.0m (96.8%), other digital assets mining $0.5m, other revenue $4.8m incl. Exaion; hosting revenue ended in Q1 2026 when the last hosting agreement expired.
  • Revenue FY2021 $159.2m to FY2025 $907.1m, +38.2% in FY2025; TTM Q3 2026 $716.0m; 9M 2026 $513.7m, (27.1%). Revenue by region is not disclosed; operations are in the US, the UAE (20% equity investee), Paraguay and France (Exaion).
  • Accounting: bitcoin is carried at fair value from FY2023 (cost less impairment in FY2021 and FY2022). Gains and losses on bitcoin held sit in operating income; the fair value change on loaned and pledged bitcoin (digital assets receivable) sits below it.
Figure 1.1 Revenue and operating margin incl. bitcoin fair value changes, FY2021 to TTM Q3 2026
Table 1.1 Revenue by type, last five quarters ($m)
Revenue lineQ3 2025Q4 2025Q1 2026Q2 2026Q3 2026Change (%)
Mining, bitcoin and other digital assets246.0195.7172.6170.3159.4(35.2%)
Hosting services1.21.21.10.00.0n/a
Other revenue, incl. Exaion5.35.41.04.64.8(8.5%)
Total revenue252.4202.3174.6174.9164.2(34.9%)
Mining includes other digital assets mining ($0.5m in Q3 2026, $3.9m in Q3 2025). Bitcoin only mining revenue $242.0m in Q3 2025 and $159.0m in Q3 2026. Q4 2025 derived as FY2025 less 9M 2025.
Table 1.2 Revenue by type, FY2024 and FY2025 ($m)
Revenue lineFY2024FY2025Change (%)
Bitcoin mining revenue599.4872.4+45.5%
Other digital assets mining revenue23.011.6(49.7%)
Hosting services31.64.7(85.2%)
Other revenue2.318.4+709.1%
Total revenue656.4907.1+38.2%
Form 10-K FY2025, MD&A.

2 Bitcoin Mining: More Hashrate, Fewer Dollars per Coin

  • Bitcoin mining revenue $159.0m in Q3 2026, (34.3%), and $501.2m in 9M 2026, (26.1%); FY2025 $872.4m, +45.5%.
  • Volume up, price down: 2,247 BTC mined in Q3 2026 against 2,144 (+4.8%) and 6,916 in 9M 2026 against 6,788; average price of BTC mined $71,688 against $114,440 ((37.4%)).
  • Fleet: energized hashrate 71.2 EH/s at 30 Sep 2026 against 60.4 EH/s, after a peak of 72.2 EH/s at 31 Mar 2026; fleet efficiency 16.9 J/TH against 18.6 J/TH a year earlier; share of available miner rewards 5.4% against 5.0%.
  • Cost per coin: purchased energy $39,674 per BTC at owned sites against $39,235; 9M 2026 $39,445 against $36,118. This measure excludes third party hosting ($71.5m in Q3 2026), maintenance and depreciation. Cost per petahash per day, which includes energy, hosting and cash maintenance, $30.8 against $31.3.
Figure 2.1 BTC produced and energized hashrate, quarterly
Table 2.1 Mining operations, last five quarters
MeasureQ3 2025Q4 2025Q1 2026Q2 2026Q3 2026
BTC produced2,1442,0112,2472,4222,247
Blocks won633595653700644
Share of available miner rewards (%)5.04.85.55.95.4
Energized hashrate at quarter end (EH/s)60.466.472.270.371.2
Purchased energy cost per BTC, owned sites ($)39,23548,61140,04738,69039,674
Cost per petahash per day ($)31.330.527.627.730.8
Mining revenue, bitcoin and other digital assets ($m)246.0195.7172.6170.3159.4
Purchased energy cost per BTC is amounts paid to power providers divided by BTC produced at owned sites, as filed; Q2 2025 not found. Cost per petahash per day includes energy, hosting and cash operating costs. Energized hashrate is theoretical capacity per manufacturer specifications.

How bitcoin mining is changing

  • Block subsidy: 3.125 BTC since the Apr 2024 halving; the next halving is expected around Apr 2028 (10-K FY2025).
  • Bitcoin price per MARA filings: $114,068 at 30 Sep 2025, $87,498 at 31 Dec 2025, $68,222 at 31 Mar 2026, $58,524 at 30 Jun 2026 and $83,556 at 30 Sep 2026.
  • Difficulty against fleet growth: MARA's purchased energy cost per BTC rose to $39,445 in 9M 2026 from $36,118 as network difficulty outpaced its hashrate growth (10-Q Q3 2026); transaction fees were 0.7% of its rewards in Q3 2026 against 0.9%.
  • Miners shift capacity away from mining: IREN aims to substantially complete its move to AI Cloud by 31 Dec 2026; Cipher stopped mining at Black Pearl in Feb 2026; Core Scientific self mining revenue fell to $12.3m in Q3 2026 from $57.4m (company Forms 10-Q).
  • Cost per BTC across miners (definitions differ): MARA $39,674 (purchased energy, owned sites), Riot $39,265 (excl. depreciation), CleanSpark $44,317 (energy, Jun 2026 quarter); revenue per BTC $70,855 to $71,692.
Figure 2.2 Cost per BTC against revenue per BTC, latest filed quarter
Figure 2.3 Bitcoin mining revenue by company, latest filed quarter
Table 2.2 Bitcoin mining by company, latest filed quarter
CompanyPeriodMetricValueChange year on year (%)Filed detail
MARAQ3 2026Bitcoin mining revenue$159.0m(34.3%)2,247 BTC mined; 71.2 EH/s energized
Riot PlatformsQ3 2026Bitcoin mining revenue$116.0mn/a1,637 BTC mined; 44.9 EH/s deployed; cost to mine $39,265 per BTC ex depreciation (55.4% of production value $70,855)
CleanSparkJun 2026 quarterBitcoin mining revenue$138.0m(30.5%)42.6 EH/s average in June 2026; energy cost $44,317 per BTC mined; average revenue $71,692 per BTC
Cipher DigitalQ3 2026Bitcoin mining revenue$20.8m(70.9%)Mining only at Odessa (about 207 MW) after Black Pearl conversion to HPC; 1,095 BTC mined in 9M 2026
Core ScientificQ3 2026Self mining revenue$12.3m(78.6%)BTC mined down 66% year on year; $266.5m impairment on mining assets in 9M 2026
IRENSep 2026 quarterBitcoin mining revenue$28.0m(88.0%)402 BTC mined against 2,039; average operating hashrate 8.8 EH/s against 45.3 EH/s
Hut 8Q3 2026BTC mined (mostly via American Bitcoin)891 BTC+54.2%Average revenue per BTC about $71,087 against $114,121
Riot mining revenue change not computed as its Q3 2025 segment value was not extracted. Hut 8 mining runs mostly through its consolidated subsidiary American Bitcoin. Each company's latest Form 10-Q, listed in the Sources appendix.

3 Bitcoin Treasury: From Holding to Selling

  • Holdings 34,012 BTC at 30 Sep 2026, against 52,850 a year earlier and 53,822 at 31 Dec 2025; fair value $2.84bn at $83,556 per BTC against a cost of $2.70bn. Split: 14,752 unrestricted, 1,408 loaned and 17,852 pledged (17,477 for the $750m loans, 375 other).
  • Sales replaced purchases: no bitcoin bought in 2026 after 4,267 BTC in FY2025; 20,880 BTC sold in Q1, 2,213 in Q2 (derived) and 3,891 in Q3 2026, 26,984 in total for $1.92bn; 15,133 of the Q1 sales funded the Mar 2026 note repurchase.
  • After 30 Sep 2026 (disclosed 9 Nov 2026): 13,597 BTC sold for about $1.1bn (about $81,039 each); the $750m of bitcoin backed loans repaid and 17,477 BTC returned; less than 5% of holdings loaned or pledged afterwards. Holdings after the sale were about 20,415 BTC before production after 30 Sep 2026 (computed; the post sale split is not filed).
  • Fair value change: $885.3m gain in Q3 2026 against $343.1m in Q3 2025; ($476.3m) in 9M 2026 and ($425.7m) in FY2025. Interest on loaned BTC $2.5m in Q3 2026 against $9.6m.
  • Funding: at the market sales fell to $46.5m gross in 9M 2026 (Jul 2026 only) from $568.6m in FY2025; convertible note principal fell from $3.30bn at 31 Dec 2025 to $2.30bn.
Figure 3.1 BTC held at quarter end and BTC price used for fair value
Table 3.1 BTC held at quarter end
MeasureDec 2024Mar 2025Jun 2025Sep 2025Dec 2025Mar 2026Jun 2026Sep 2026
BTC held incl. loaned and pledged44,89347,53149,95152,85053,82235,30335,57734,012
BTC price used for fair value ($)93,35482,534107,173114,06887,49868,22258,52483,556
Fair value of holdings ($bn, computed)4.193.925.356.034.712.412.082.84
Holdings incl. loaned and pledged BTC; exclude 36 BTC held by the ADGM equity investee. Fair value computed as BTC held times the price used for fair value; filed fair value $2.84bn at 30 Sep 2026 and $4.71bn at 31 Dec 2025.
Table 3.2 Convertible senior notes at 30 Sep 2026
SeriesPrincipal ($m)Conversion price ($)Holder put
1.00% notes due Dec 202648.176.17none; matures 1 Dec 2026
2.125% notes due Sep 2031300.018.891 Mar 2029
0.00% notes due Mar 2030632.525.911 Dec 2027
0.00% notes due Jun 2031291.634.584 Jun 2027 and 4 Jun 2029
0.00% notes due Aug 20321,025.020.264 Jan 2030 (if share price below conversion price)
Total principal $2.30bn; original principal $1.0bn for the Mar 2030 notes and $925m for the Jun 2031 notes before the Mar 2026 repurchase. Aug 2032 notes carry a capped call with a $24.14 cap.

How bitcoin treasuries are changing

  • Strategy keeps buying: 847,666 BTC at 30 Sep 2026 at an average cost of $75,437 ($63.95bn), fair value $70.82bn; $14.26bn of bitcoin bought and 5,552 BTC sold in 9M 2026 (Form 10-Q, 2 Nov 2026).
  • Miners sell what they mine: Riot sold 20,264 BTC for about $1.5bn in 9M 2026 and held 2,418 BTC at 30 Sep 2026; IREN sells all bitcoin it mines daily and held none; Core Scientific held 32 BTC.
  • Others hold and pledge: Hut 8 held 16,787 BTC with 4,850 pledged for a term loan, and sold about 954 BTC in Q3 and 2,148 BTC in Oct 2026 to fund share repurchases; CleanSpark held about 12,205 BTC plus 1,719 posted as collateral at 30 Jun 2026.
Figure 3.2 BTC held by company, latest filed quarter end
Table 3.3 BTC held by company, latest filed quarter end
CompanyDateBTC heldChange year on year (%)Filed detail
MARA30 Sep 202634,012(35.6%)20,415 after the 13,597 BTC sale, before BTC mined after 30 Sep 2026 (computed)
Strategy30 Sep 2026847,666n/aAverage cost $75,437; fair value $70.82bn
Hut 830 Sep 202616,787+62.3%4,850 BTC pledged for FalconX term loan
CleanSpark30 Jun 202612,205n/aPlus 1,719 BTC receivable posted as collateral
Riot Platforms30 Sep 20262,418(87.5%)19,287 BTC a year earlier
Cipher Digital30 Sep 2026310n/a1,433 BTC at 31 Dec 2025
Core Scientific30 Sep 202632n/a2,537 BTC at 31 Dec 2025
Each company's latest Form 10-Q, listed in the Sources appendix. Strategy is shown for comparison as a bitcoin treasury company.

4 AI, HPC and Power: 1.9 GW Today, Leases Still to Sign

  • Power base: about 1.9 GW of total energy capacity at 30 Sep 2026 (1.7 GW a year earlier); path to about 4.8 GW if Long Ridge closes and Matagorda power is allocated (10-Q Q3 2026).
  • Exaion: 64% bought on 20 Feb 2026 for $174.5m; a four year $79m GPU as a service contract at 100% take or pay with its first US customer (Q3 2026 letter); indicated pipeline over $3bn, which the letter describes as not yet contracted. Other revenue, which includes Exaion, $4.8m in Q3 2026.
  • Long Ridge (Ohio): 485 MW gas plant, 505 MW nameplate expected in 1H 2027, over 1,600 acres; about $1.5bn incl. debt; about 70% of output under long term contracts; FERC approval on 4 Nov 2026; closing pending at 12 Nov 2026.
  • Matagorda County (Texas): rights to up to 2,000 MW and up to $600m of milestone payments, none paid; classified as studied load in ERCOT Batch Zero, with a Texas audit of data center projects ordered on 3 Aug 2026.
  • Starwood: joint ventures per site with MARA holding 10% to 50%; over 1 GW of initial IT capacity; $17.7m of a $136.3m predevelopment budget incurred; no leases signed, two targeted before end 2026 with timing that could slip into 2027.
Figure 4.2 Total energy capacity and miner fleet efficiency
Table 4.1 AI, HPC and power projects as filed
ProjectStatus at 9 Nov 2026
Exaion (France)64% owned since 20 Feb 2026; $79m four year GPU as a service contract, 100% take or pay; customers indicated demand for over 30 MW of compute by end 2027
Starwood joint venturesagreement of 26 Feb 2026; MARA 10% to 50% per site; over 1 GW initial IT capacity, path beyond 2.5 GW; no leases signed
Long Ridge (Hannibal, Ohio)about $1.5bn; 485 MW authorized, 505 MW nameplate expected 1H 2027; annualized adjusted EBITDA about $143.9m in 2H 2025; FERC approval 4 Nov 2026; closing pending at 12 Nov 2026
Matagorda County (Texas)rights to up to 2,000 MW; up to $600m milestones, none paid; $100m deposit replaced by a letter of credit in Oct 2026; ERCOT Batch Zero and Texas audit pending
Vertebraiflexible compute platform; Texas wind farm curtailment cut from an estimated 46% to 22% from Apr to Sep 2026
Granbury AI inferencefirst ten racks (Q3 2025 letter); no material revenue (10-K FY2025)
Forms 8-K of 26 Feb, 30 Apr, 9 Jul, 25 Sep and 9 Nov 2026; Forms 10-Q for Q1 to Q3 2026.

How the market for AI data center sites is changing

  • Leases at former mining sites: Core Scientific had about 485 MW of 590 MW contracted with CoreWeave billing at 30 Sep 2026 and signed a 530 MW contract with AMD and a neocloud in Jul 2026; Riot announced a 910 MW lease at Corsicana with an AI lab in Nov 2026; CleanSpark signed a 20 year lease for 175 MW at Sandersville, Georgia on 10 Jul 2026.
  • Revenue has started at some peers: IREN AI Cloud revenue $200m of $228m in the Sep 2026 quarter after Microsoft accepted Horizon 1 in Aug 2026; Cipher Digital began lease revenue at Black Pearl in Aug 2026 ($5.9m in Q3 2026).
  • Pipelines: Hut 8 reports 1,330 MW under construction and an 8,569 MW pipeline; IREN about 5 GW of grid connection rights; Cipher 4.3 GW of grid capacity.
  • Texas review: the Governor directed PUCT and ERCOT on 3 Aug 2026 to audit all data center projects in the interconnection queue, and ERCOT postponed Batch Zero milestones (10-Q Q3 2026).
Figure 4.1 AI and HPC revenue by company, latest filed quarter
Table 4.2 AI and HPC by company, latest filed quarter
CompanyPeriodMetricValueFiled detail
MARAQ3 2026AI and HPC lease revenue$0.0mNo leases signed; Exaion $79m 4 year GPU contract; Long Ridge pending close
Core ScientificQ3 2026Colocation revenue$215.4mAbout 485 MW billing for CoreWeave
IRENSep 2026 quarterAI Cloud revenue$200.0m$65m AI Cloud lease revenue incl. Microsoft
Hut 8Q3 2026HPC colocation and cloud revenue$68.4m$1.07bn revolving credit facility Sep 2026
Riot PlatformsQ3 2026Data center revenue$18.4m910 MW Corsicana lease announced Nov 2026
Cipher DigitalQ3 2026HPC leasing revenue$5.9mFirst lease revenue Aug 2026; $850m 0% converts issued Oct 2026
CleanSparkJul 2026Contracted critical IT load175 MW20 year lease at Sandersville; 1,817 MW contracted power
Line items as each company files them; each company's latest Form 10-Q, listed in the Sources appendix.

5 Financial Analysis & Ratios

  • Operating income $176.5m in Q3 2026 against $47.6m in Q3 2025; it includes a $421.9m gain on digital assets, so costs and expenses net of that gain were $(12.3)m as filed and $409.5m before it (computed). TTM operating loss ($2.82bn) and net loss ($2.94bn) include a fair value loss of ($1.93bn).
  • Margins above 100%: total costs and expenses are negative in Q3 2026 because the $421.9m bitcoin gain is netted against them, so operating income ($176.5m) exceeds revenue ($164.2m). The operating margin of 107.5% and net margin of 386.3% in Table 5.2 reflect that gain; excluding it, operating income was ($245.3m).
  • Items in Q3 2026: restructuring $19.0m (Project Align); unrealized loss on the power swap derivative $19.0m; general and administrative $75.8m against $85.3m. In 9M 2026: restructuring $66.6m, accelerated depreciation of mining rigs $48.2m, a $10.2m patent settlement, $28.4m of acquisition and integration costs, a $61.8m loss on the power swap and a $70.6m gain on the Mar 2026 note repurchase.
  • Cash flow: operating cash flow ($642.7m) in 9M 2026; proceeds of $1.92bn from bitcoin sales are investing cash flows, so operating cash flow excludes monetized production. Capital expenditure, computed as purchases of property and equipment plus miner vendor deposits, $113.0m in Q3 2026 and $317.1m TTM.
  • Balance sheet at 30 Sep 2026: cash $946.5m against $547.1m at 31 Dec 2025 (11% in euros at Exaion); bitcoin $2.84bn at fair value; debt principal $3.05bn (convertible notes $2.30bn and $750m of bitcoin backed loans), carrying value $3.02bn; equity $2.35bn; redeemable noncontrolling interest $80.4m (Exaion minority put).
  • Capital returns: no dividend; share buybacks $46.9m in FY2025; a repurchase program of up to $500m was authorized on 9 Nov 2026.
Table 5.1 Income statement, cash flow and balance sheet summary ($bn unless stated)
Line itemFY2021FY2022FY2023FY2024FY2025TTM Q3 2026
Revenue0.20.10.40.70.90.7
Gross profit0.10.00.0(0.2)(0.4)(0.7)
Research and developmentn/an/a0.00.00.00.0
Selling, general and administrative0.20.10.10.30.30.4
Operating income0.0(0.7)0.20.3(1.2)(2.8)
Net income0.0(0.7)0.30.5(1.3)(2.9)
Diluted EPS ($)(0.30)(6.12)1.061.72(3.69)(8.15)
Operating cash flow0.0(0.2)(0.3)(0.7)(0.8)(0.9)
Capital expenditure(0.7)(0.5)(0.2)(1.1)(0.6)(0.3)
Free cash flow(0.7)(0.7)(0.5)(1.7)(1.4)(1.2)
Stock based compensation0.20.00.00.20.20.1
Cash and investmentsn/a0.10.40.40.50.9
Total debtn/a0.80.32.43.63.0
Total equity0.70.41.64.13.52.4
Gross profit is computed: revenue less purchased energy, operating and maintenance, third party hosting and other energy, and depreciation; MARA files no cost of revenue or gross profit line from FY2023. Capital expenditure is computed as purchases of property and equipment plus deposits and payments to miner vendors; Q4 2025 vendor deposits are derived as FY less 9M (negative $62.3m after a reclassification), so TTM capex is understated by that amount against a gross figure. Operating and net income include bitcoin fair value changes from FY2023 and impairment before. TTM equals Q4 2025 plus Q1 to Q3 2026; cash is cash and cash equivalents; debt is carrying value. See Table 5.5 for the same lines in $m.
Figure 5.1 Quarterly revenue and margins
Table 5.2 What changed, Q3 2026 against Q3 2025
MetricQ3 2025Q3 2026Change
Revenue ($bn)0.250.16(34.9%)
Gross profit ($bn)(0.06)(0.13)(113.0%)
Operating income ($bn)0.050.18271.0%
Net income ($bn)0.120.63415.2%
Diluted EPS ($)0.271.28374.1%
Operating cash flow ($bn)(0.20)(0.17)13.8%
Free cash flow ($bn)(0.39)(0.28)27.2%
Operating margin (%)18.9107.588.6 pts
Net margin (%)48.8386.3337.5 pts
Table 5.3 Ratio analysis
RatioFY2021FY2022FY2023FY2024FY2025TTM Q3 2026
Growth and margins
Revenue growth (%)n/a(26.0)229.169.438.2n/a
Gross margin (%)73.4(28.6)(4.8)(29.3)(47.7)(94.4)
Operating margin (%)(1.9)(572.0)57.046.6(135.0)(393.4)
Net margin (%)(18.7)(589.4)66.982.5(144.6)(411.2)
FCF margin (%)(457.3)(595.7)(129.6)(265.9)(150.3)(165.4)
Cost and investment intensity
R&D (%) revenuen/an/a0.72.03.33.0
SBC (%) revenue101.020.98.424.019.019.0
Capex (%) revenue445.4445.848.1162.761.844.3
Returns
ROE (%)(4.3)(129.1)25.918.8(34.5)(125.1)
ROA (%)n/a(58.1)16.312.3(18.6)(51.9)
Liquidity and leverage
Current ratio (x)n/a10.6330.514.941.272.31
Debt to equity (x)n/a2.030.200.591.041.28
Net cash ($bn)n/a(0.7)0.0(2.1)(3.1)(2.1)
Gross margin uses computed gross profit. Operating and net margins include bitcoin fair value changes and swing far beyond (100%). ROE and ROA use average balances for FY2023 to FY2025 and period end balances for TTM; FY2021 balance sheet lines are not available. Net cash is cash less debt and excludes bitcoin.
Figure 5.2 Operating cash flow, capital expenditure and free cash flow
Table 5.4 Valuation snapshot at $7.66 per share, 11 Nov 2026 (computed)
MeasureValue
Market value ($bn)3.0
Enterprise value, debt principal less cash ($bn)5.1
Bitcoin at fair value, 30 Sep 2026 ($bn)2.8
Enterprise value less bitcoin ($bn)2.2
Enterprise value less bitcoin to TTM revenue (x)3.1
Market value to bitcoin fair value (x)1.0
Price to book value (x)1.3
Table 5.5 Annual results in $m, FY2021 to TTM Q3 2026
Line ($m)FY2021FY2022FY2023FY2024FY2025TTM Q3 2026
Revenue159.2117.8387.5656.4907.1716.0
Cost of revenue incl. depreciation (computed)42.4151.4406.2848.41,340.01,391.9
Gross profit (computed)116.8(33.7)(18.7)(192.1)(432.9)(675.8)
Research and developmentn/an/a2.813.230.121.5
General and administrative174.456.783.6254.0349.9363.2
Depreciation and amortization14.978.7179.6429.2772.8802.9
Fair value change on bitcoin incl. loaned and pledgedn/an/a331.51,113.6(425.7)(1,927.4)
Operating income(3.0)(673.5)220.9306.1(1,224.3)(2,816.6)
Interest expense1.615.010.413.048.443.3
Net income(29.8)(694.0)259.1541.3(1,311.5)(2,944.6)
Stock based compensation160.824.632.6157.6172.3135.7
Capital expenditure incl. miner deposits (computed)(708.9)(524.9)(186.6)(1,068.1)(560.3)(317.1)
Adjusted EBITDA (company measure)n/an/a415.11,235.0(330.8)n/a
$m version of Table 5.1 for lines that round to $0.0bn. Cost of revenue is purchased energy, operating and maintenance, third party hosting and other energy, and depreciation; FY2021 and FY2022 use the filed cost of revenues. TTM equals Q4 2025 plus Q1 to Q3 2026. Q4 2025 adjusted EBITDA was stated only as ($1.5bn), so no TTM figure is shown.
Table 5.6 Quarterly results, last five quarters ($m)
Line ($m)Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Revenue252.4202.3174.6174.9164.2
Purchased energy43.150.844.748.848.1
Third party hosting and other energy75.779.470.069.271.5
Operating and maintenance26.327.530.626.921.5
Depreciation and amortization167.3285.8191.6174.7150.9
Gross profit (computed)(60.0)(241.1)(162.4)(144.6)(127.7)
Fair value change on bitcoin incl. loaned and pledged343.1(1,451.1)(1,018.6)(343.0)885.3
Operating income47.6(1,410.6)(1,061.5)(521.1)176.5
Net income attributable to MARA123.1(1,709.6)(1,259.6)(609.7)634.4
Diluted EPS ($)0.27(4.52)(3.31)(1.60)1.28
Adjusted EBITDA (company measure)395.6(1,500.0)(1,000.0)(360.9)857.7
Operating cash flow(199.0)(224.7)(247.5)(223.8)(171.5)
Capital expenditure incl. miner deposits (computed)(192.0)(102.2)(80.2)(21.7)(113.0)
Q4 2025 equals FY2025 less 9M 2025. Q4 2025 and Q1 2026 adjusted EBITDA as rounded in the shareholder letters. Net income is attributable to MARA; Q3 2026 net income incl. noncontrolling interests $632.1m.

Cost structure and profitability

  • Cost of revenue lines, Q3 2026 against Q3 2025: purchased energy $48.1m against $43.1m; third party hosting and other energy $71.5m against $75.7m; operating and maintenance $21.5m against $26.3m; depreciation and amortization $150.9m against $167.3m.
  • Gross profit (computed) ($127.7m) in Q3 2026 against ($60.0m); before depreciation $23.1m. Every quarter since Q1 2025 shows a computed gross loss after depreciation.
  • Fair value changes set the sign of net income: gains of $1.19bn in Q2 2025 and $885.3m in Q3 2026 and losses of ($1.45bn) in Q4 2025 and ($1.02bn) in Q1 2026; net income moved with them.
Figure 5.3 Cost of revenue lines against revenue, quarterly
Figure 5.4 Fair value change on bitcoin and net income, quarterly

6 MD&A & Management Commentary

Q3 2026 Form 10-Q and shareholder letter (8-K Ex 99.1 of 9 Nov 2026)

  • Q3 2026 (9 Nov 2026): revenue $164.2m, (34.9%); a 37% lower average price of BTC mined cut revenue by $94.8m and higher production added $11.7m. Net income $632.1m incl. noncontrolling interests ($634.4m attributable to MARA), diluted EPS $1.28; adjusted EBITDA $857.7m against $395.6m.
  • Production: 2,247 BTC mined (24.4 per day), 644 blocks won, 5.4% of available miner rewards against 5.0%; no bitcoin bought; energized hashrate 71.2 EH/s, +17.9%; fleet efficiency 16.9 J/TH.
  • Costs: purchased energy $39,674 per BTC at owned sites; direct energy cost $0.04 per kWh; cost per petahash per day $30.8 against $31.3; energy cost 54.6% of owned mining revenue against 34.3%. Third party hosting arrangements covering about 29% of energy capacity expire from Q3 2027 to Q1 2028.
  • Bitcoin and debt: 3,891 BTC sold in Q3 2026 at an average $75,300; $750m of bitcoin backed borrowings ($600m new, $150m refinanced) funded the Long Ridge purchase. After 30 Sep 2026, 13,597 BTC were sold at about $81,039, the loans were repaid, 17,477 pledged BTC returned and less than 5% of holdings stayed loaned or pledged; the company estimates a net benefit of $170m from borrowing near $64,000 and selling near $81,039. Total debt fell $1.4bn, or 37%, in 2026.
  • Liquidity (10-Q): cash plus bitcoin about $3.8bn; contractual obligations $3.66bn incl. $2.33bn of convertible note principal and interest; hosting contracts about $250.6m over 18 months; miner purchase commitments $28.7m.
  • Earlier 2026 quarters: Q2 (6 Aug 2026) revenue $174.9m, (27%), net loss ($611.3m), adjusted EBITDA ($360.9m), 2,422 BTC mined; Q1 (11 May 2026) revenue $174.6m, (18%), net loss ($1.26bn) attributable, 20,880 BTC sold at an average $70,137 and about 30% of convertible debt retired at a 9% discount to par.
  • No transcript of the 9 Nov 2026 call was found; management statements below come from the shareholder letters filed as Exhibit 99.1.
Table 6.1 Company targets and dates as filed
ItemOutlookSource
Financial guidanceno revenue or EBITDA guidance issuedForms 8-K and 10-Q, 2026
Lease signingstargeting two leases before year end 2026; timing could slip into 20278-K Ex 99.1, 9 Nov 2026
Long Ridge closingFERC approval 4 Nov 2026; closing expected in the coming weeks; outside date 30 Nov 2026, extendable to 30 Jun 202710-Q Q3 2026; 8-K of 30 Apr 2026
Long Ridge plant and AI load485 MW authorized, 505 MW nameplate expected in 1H 2027 (Q1 2027 in the Q2 2026 Form 10-Q, 2H 2026 in the Q1 2026 Form 10-Q); AI and critical IT construction from 1H 2027, ready mid 2028, up to 600 gross MW10-Q Q1 to Q3 2026; 8-K Ex 99.1, 30 Apr 2026
Power portfolioabout 1.9 GW today; path to about 4.8 GW with Long Ridge and Matagorda10-Q Q3 2026
MatagordaERCOT Batch Zero study due 1H 2027; Texas audit of data center projects ordered 3 Aug 202610-Q Q3 2026
Exaion demandindicated pipeline over $3bn, about $1bn targeted for delivery by end 2027; described as not yet contracted8-K Ex 99.1, 9 Nov 2026
Third party hostingarrangements covering about 29% of energy capacity expire Q3 2027 to Q1 202810-Q Q3 2026

Management and CFO commentary

  • CFO Salman Khan, Q3 2026 letter (9 Nov 2026): cash $946.5m against $547.1m at 31 Dec 2025, cash plus bitcoin about $3.8bn; 3.8m shares sold under the at the market program in Jul 2026 with about $1.5bn of capacity left; 1,408 BTC loaned, earning $2.5m of interest in Q3; total debt down $1.4bn, or 37%, in 2026.
  • CEO Fred Thiel, Q3 2026 letter: strategy to raise the value of each megawatt controlled, with bitcoin mining as the core; customers favour sites with power on a firm schedule; Long Ridge has over 1 GW of total potential capacity with the existing mining there; contracts are prioritized when they can be financed at acceptable returns.
  • Q3 2026 letter, AI and HPC: Vertebrai cut curtailment at a Texas wind farm from an estimated 46% to 22% of potential generation from Apr to Sep 2026; investor sentiment on AI infrastructure described as more cautious on adoption pace, community opposition, financing costs and credit structures.
  • Q2 2026 letter (6 Aug 2026): 35,577 BTC held (about $2.1bn), incl. 9,270 loaned or pledged; 4,742 BTC loaned earning $4.3m; general and administrative costs excluding stock compensation $69.5m incl. $15.4m of acquisition costs and the $10.2m litigation settlement; two bitcoin backed facilities after 30 Jun 2026 at a 7.56% weighted cost for $600m of new borrowing.
  • Q1 2026 letter (11 May 2026): 20,880 BTC sold at an average $70,137; about 30% of convertible debt retired at a 9% discount to par; $150m refinanced at 7% against 10.5%; workforce cut 15% for $12m of annualized savings.
  • CEO, Long Ridge release (8-K Ex 99.1, 30 Apr 2026): the purchase raises owned and operated capacity about 65% and operational and development capacity to about 2.2 GW; Long Ridge annualized adjusted EBITDA about $143.9m in 2H 2025 with all in operating cost below $15 per MWh.
Table 6.2 Management statements in their own words
SpeakerDate and sourceStatement
Fred Thiel, Chairman and CEO9 Nov 2026, Q3 2026 shareholder letter, 8-K Ex 99.1“Bitcoin built the foundation. Power created the opportunity.”
Fred Thiel, Chairman and CEO9 Nov 2026, Q3 2026 shareholder letter, 8-K Ex 99.1“In our experience, waiting has improved the terms available to us.”
Fred Thiel, Chairman and CEO30 Apr 2026, Long Ridge release, 8-K Ex 99.1“Power is the scarce input in AI”
Table 6.3 Key disclosures in the Forms 10-K and 10-Q
ItemDisclosure
10-Q Q3 2026, results9M 2026 revenue $513.7m, (27%); 6,916 BTC mined, +2%; average price mined $73,048, (28%); 9M net loss ($1.24bn) after a ($476.3m) fair value change, $517.1m of depreciation (incl. $48.2m accelerated) and $66.6m of restructuring.
10-Q Q3 2026, debt$291.6m of Jun 2031 notes classified current because of the 4 Jun 2027 put; $48.1m of Dec 2026 notes mature 1 Dec 2026; Mar 2030 notes ($632.5m) puttable 1 Dec 2027; conversion prices $18.89 to $76.17, all above the $7.66 share price of 11 Nov 2026.
10-Q Q3 2026, commitmentsStarwood approved predevelopment budget $136.3m, $17.7m incurred; Matagorda milestone payments up to $600m, none paid; $100m interconnection deposit replaced by a letter of credit on 23 Oct 2026.
10-Q Q3 2026, legalSecurities class action dismissed with prejudice on 31 Mar 2026; appeal briefing to conclude 13 Nov 2026; derivative suits pending.
10-K FY2025, operations18 data centers, about 1.9 GW, about 490,000 rigs, 66.4 EH/s; owned operational capacity 779 MW of 1,324 MW, hosted 536 MW; six US patents.
10-K FY2025, resultsRevenue $907.1m (bitcoin mining $872.4m); 8,799 BTC mined at an average $101,221; purchased energy per BTC $38,956; energy cost 38.5% of owned mining revenue against 40.8%; adjusted EBITDA ($330.8m).
10-K FY2025, chargesImpairment of goodwill and other assets $109.0m; accelerated depreciation of mining rigs $110.5m in Q4 2025; debt $3.6bn at 31 Dec 2025 (convertible notes $3.30bn principal and a $350m credit line).

7 Sector & Competitor Analysis

  • Sector: listed bitcoin miners that are turning sites and power into data centers for AI and HPC. Peers from their latest Forms 10-Q: Riot Platforms, CleanSpark (Jun 2026 quarter, fiscal year to Sep), Cipher Digital, Core Scientific, IREN (Sep 2026 quarter, fiscal year to Jun) and Hut 8, with Strategy for the bitcoin treasury.
  • Revenue, latest quarter: Core Scientific $232.9m (+187.1%), IREN $228.0m ((5.0%)), Riot $181.4m (+0.7%), MARA $164.2m ((34.9%)), CleanSpark $138.0m of bitcoin mining revenue in the Jun 2026 quarter ((30.5%)), Hut 8 $71.1m ((14.9%)), Cipher $26.7m ((62.8%)). IREN covers the Sep 2026 quarter.
  • Mining scale: MARA produced 2,247 BTC on 71.2 EH/s; Riot 1,637 BTC on 44.9 EH/s; Hut 8 891 BTC, mostly through American Bitcoin; IREN 402 BTC in the Sep 2026 quarter against 2,039 a year earlier.
  • Bitcoin held at the latest quarter end: Strategy 847,666; MARA 34,012; Hut 8 16,787; CleanSpark 12,205 (Jun 2026); Riot 2,418; Cipher 310; Core Scientific 32; IREN none.
  • Leverage: cash as a share of debt ranged from 2% at Hut 8 to 99% at Riot; MARA 31% (cash $946.5m against debt $3.05bn). Peer share prices were not collected, so no peer valuation ratios are shown.
Table 7.1 Peer comparison, latest filed quarter
CompanyRevenue growth (%)Net cash ($bn)
MARA(34.9)(2.1)
RIOT0.70.0
CLSK(30.5)(1.6)
CIFR(62.8)(5.4)
CORZ187.1(3.6)
IREN(5.0)(6.5)
HUT(14.9)(7.6)
MSTR(2.5)(4.2)
Revenue growth is year on year for the latest filed quarter: CleanSpark Jun 2026 quarter, IREN Sep 2026 quarter (Q1 FY2027), others Q3 2026. Net cash is cash less debt at the same quarter end and excludes bitcoin. Peer TTM statements and peer share prices were not collected; see Table 7.2 for quarterly lines. Figure 7.1 draws every company with the same bubble size because peer market values were not collected.
Figure 7.1 Revenue growth versus operating margin, peer set
Table 7.2 Bitcoin miners and Strategy, latest filed quarter ($m unless stated)
CompanyQuarterRevenueChange (%)Operating incomeNet incomeBTC heldHashrate (EH/s)BTC minedCashDebt
MARA HoldingsQ3 2026164.2(34.9%)176.5634.434,01271.22,247946.53,047.2
Riot PlatformsQ3 2026181.4+0.7%1.24.02,41844.91,637669.1674.5
CleanSparkJun 2026 quarter138.0(30.5%)(232.4)(239.8)12,20542.6n/a202.61,782.4
Cipher DigitalQ3 202626.7(62.8%)(71.9)31.6310n/an/a656.06,016.3
Core ScientificQ3 2026232.9+187.1%72.41,178.132n/an/a803.94,385.0
IRENSep 2026 quarter228.0(5.0%)(186.0)(263.0)07.94023,522.010,041.0
Hut 8Q3 202671.1(14.9%)318.2131.116,787n/a891156.97,726.4
StrategyQ3 2026125.4(2.5%)20,909.819,533.0847,666n/an/a2,501.56,715.4
Single quarter figures from each company's latest Form 10-Q. Operating and net income include bitcoin fair value changes where held. CleanSpark revenue is its bitcoin mining line; IREN hashrate is its Sep 2026 quarter end figure. Hashrate not shown where the MD&A read gives none or where not applicable.

8 Material Events & Contracts

  • 13 Forms 8-K from 12 Nov 2025 to 12 Nov 2026, no amendments: four results filings with shareholder letters (Ex 99.1), the Starwood agreement, the Long Ridge purchase and its investor presentation, the Matagorda (HIF) purchase and its amendment, the Mar 2026 note repurchase with bitcoin sales, new equity award forms, board changes and the annual meeting results.
  • Long Ridge: agreement of 30 Apr 2026 to buy Long Ridge Energy & Power from FTAI Infrastructure for about $1.5bn incl. debt; FERC approval on 4 Nov 2026; closing pending at 12 Nov 2026.
  • Board: directors Barbara Humpton and Georges Antoun resigned effective 31 Jul 2026; Nancy Novak and Craig Hart joined on 1 Aug 2026.
Table 8.1 Forms 8-K filed from 12 Nov 2025 to 12 Nov 2026
DateItemsEvent
25 Feb 20265.02, 9.01New 2026 RSU and PSU award forms; PSUs tied to FY2026 Economic Triad Megawatt Capacity and Annual Recurring Revenues, payout up to 249% of target, relative TSR modifier 2026 to 2028, total LTI capped at 200% of target
26 Feb 20261.01, 7.01, 9.01Strategic Agreement with Starwood to develop and lease MARA US mining sites; MARA elects 10% to 50% per JV; decision required within 24 months, extendable by 12 months
26 Feb 20262.02, 9.01Q4 2025 and FY2025 results: FY revenue $907.1m +38%, FY net loss $1.31bn, Q4 net loss $1.7bn ($4.52 per share), year end BTC 53,822
26 Mar 20268.01Repurchase of $367.5m 2030 notes for $322.9m and $633.4m 2031 notes for $589.9m; sold 15,133 BTC for about $1.1bn between 4 and 25 Mar 2026; convertible notes outstanding fall from $3.298bn to $2.297bn
30 Apr 20261.01, 7.01, 9.01Agreement to buy Long Ridge Energy & Power from FTAI Infrastructure for about $1.5bn including debt; Barclays $785m 364 day bridge commitment; $75m termination fee; outside date 30 Nov 2026 (30 Jun 2027 if regulatory conditions pending)
11 May 20262.02, 9.01Q1 2026 results: revenue $174.6m, net loss $1.26bn attributable, 20,880 BTC sold
22 Jun 20265.02, 5.07, 9.01Annual meeting 18 Jun 2026: directors elected, PwC ratified, say on pay passed, 18m shares added to 2018 equity plan
25 Jun 20268.01, 9.01Long Ridge investor presentation filed (Ex 99.1)
9 Jul 20261.01, 2.01, 7.01, 9.01Acquired MAT 1177 LLC (Matagorda County TX site, rights to 2,000 MW) from HIF; up to $600m in milestone payments
4 Aug 20265.02, 7.01, 9.01Directors Barbara Humpton and Georges Antoun resigned effective 31 Jul 2026 for personal reasons; Nancy Novak and Craig Hart appointed 1 Aug 2026
6 Aug 20262.02, 9.01Q2 2026 results: revenue $174.9m, net loss $611.3m, BTC 35,577
25 Sep 20261.01First amendment to HIF purchase agreement: $100m security deposit with utility; milestones restructured around Texas audit and interconnection study; total consideration stays up to $600m; sale process replaces reconveyance
9 Nov 20262.02, 9.01Q3 2026 shareholder letter (Ex 99.1): revenue $164.2m, net income $632.1m incl. a $885.3m fair value gain, adjusted EBITDA $857.7m; 13,597 BTC sold after 30 Sep 2026; $500m buyback authorized
Table 8.2 Material contracts and financing arrangements
ContractTerms
Convertible senior notes (five series)Principal $2.30bn at 30 Sep 2026 after the Mar 2026 repurchase of $367.5m of 2030 notes for $322.9m and $633.4m of 2031 notes for $589.9m ($70.6m gain). Holder puts: Jun 2031 notes 4 Jun 2027 ($291.6m), Mar 2030 notes 1 Dec 2027 ($632.5m), Sep 2031 notes 1 Mar 2029, Aug 2032 notes 4 Jan 2030 if the share price is below $20.26.
Bitcoin backed loansCoinbase $450m at the fed funds midpoint plus 3.875% and Two Prime $300m at 7.65%, maturing Aug 2028; secured by 17,477 BTC; repaid in full after 30 Sep 2026.
Long Ridge Equity Purchase Agreement (Ex 10.1, 30 Apr 2026)About $1.5bn incl. assumed debt of up to about $900m, incl. $600m of 8.750% senior secured notes due 2032; Barclays commitment for a 364 day bridge loan of up to $785m; $75.0m termination fee payable by MARA in some cases if not closed by 30 Nov 2026 (30 Jun 2027 if regulatory conditions are pending).
Starwood Strategic Agreement (Ex 10.1, 26 Feb 2026)Joint venture per US mining site, Starwood managing member, MARA electing 10% to 50%; over 1 GW of initial IT capacity and a path beyond 2.5 GW; decision due 24 months after closing, extendable by 12 months; if Starwood proceeds after a qualifying lease and MARA does not, MARA must sell the powered land rights to Starwood.
Matagorda County site (MAT 1177 LLC, 8-K of 9 Jul and 25 Sep 2026)Land rights and a utility letter agreement for up to 2,000 MW; up to $600m of milestone payments tied to the Texas audit and the interconnection study, none paid at 30 Sep 2026.
Exaion (64% stake, 20 Feb 2026)Bought for $174.5m (EUR 148m); goodwill $92.0m; potential further equity infusion of EUR 110m; minority put after four years ($80.4m redeemable noncontrolling interest).
At the market program (Mar 2025) and repurchase program (9 Nov 2026)$2.0bn at the market program: $568.6m sold in 2025, 3,837,765 shares for $46.5m gross in Jul 2026, about $1.5bn left at 30 Sep 2026. Share repurchase of up to $500m authorized on 9 Nov 2026.

9 Ownership, Voting Power & Annual Meeting

  • Ownership: one class of common stock, 387.4m shares at 29 Oct 2026. The beneficial ownership table of the 2026 proxy statement and 13F holdings were not parsed for this report.
  • 2026 annual meeting (18 Jun 2026): 213.4m shares represented. Vicki Mealer‑Burke was elected with 59.2% of votes for and withheld and Douglas Mellinger with 90.9%; PwC ratified with 98.0%; the advisory vote on executive pay passed with 59.1%; 18.0m shares added to the 2018 equity plan with 76.0%.
  • Equity awards (8-K, 25 Feb 2026): 2026 performance share units tied to FY2026 Economic Triad Megawatt Capacity and Annual Recurring Revenues, paying up to 249% of target with a relative shareholder return modifier for 2026 to 2028; total long term incentive payout capped at 200% of target.
  • Insiders, Forms 4 from 13 Nov 2025 to 12 Nov 2026: no open market purchases. All open market sales ($7.23m in total) were under trading plans: CEO Fred Thiel 357,565 shares ($3.79m), 27,505 shares a month at $6.79 (2 Nov 2026) to $14.25 (17 Jun 2026); CFO Salman Khan 213,464 shares ($2.32m); General Counsel Zabi Nowaid 82,468 shares ($1.01m); director Douglas Mellinger 7,000 shares at $16.00 on 22 Jun 2026 ($0.11m). Shares withheld for tax totalled $14.1m; the rest of the filings are award grants.
Table 9.1 Annual meeting vote results, 18 Jun 2026
ProposalFor (m votes)Against (m votes)Abstain (m votes)For as % of votes castResult
Elect Vicki Mealer‑Burke (Class III)65.545.10.059.2Elected
Elect Douglas Mellinger (Class III)100.510.10.090.9Elected
Ratify PwC as auditor for FY2026208.34.20.998.0Approved
Advisory vote on executive pay65.045.00.659.1Approved
Add 18.0m shares to the 2018 Equity Incentive Plan83.726.40.476.0Approved
Director votes are For and Withheld (Withheld shown as Against). Broker non votes 102.8m on each item except the auditor ratification. Two Class III directors stood for election.

Annual meeting remarks

  • No transcript or recording of management remarks at the 18 Jun 2026 meeting was found; the filings give only the vote results (8-K Item 5.07).

10 Risk Factors

  • Item 1A of the FY2025 Form 10-K holds 52 risk factors against 49 in FY2024 (12,176 words against 9,852): 8 added, 5 removed and 10 materially reworded. AI or HPC appears in 10 factors against none a year earlier.
  • The three 2026 Forms 10-Q added factors on the Long Ridge closing and its $75.0m termination fee (Q1), the Matagorda site and the Texas data center audit, and debt secured by bitcoin (Q2), and updated them in Q3.
Table 10.1 Risk factors with filed figures
RiskDisclosure and change
Bitcoin priceFair value change on bitcoin ranged from ($1.45bn) in Q4 2025 to $885.3m in Q3 2026; average price of BTC mined $71,688 in Q3 2026 against $114,440 a year earlier.
Mining economics and halvingEnergy cost 54.6% of owned mining revenue in Q3 2026 against 34.3%; block subsidy 3.125 BTC since Apr 2024, with the next halving expected around Apr 2028 (10-K FY2025).
Convertible note puts$291.6m puttable 4 Jun 2027 and $632.5m puttable 1 Dec 2027; $48.1m due 1 Dec 2026; conversion prices $18.89 to $76.17 against a share price of $7.66 on 11 Nov 2026.
Bitcoin lending and pledging1,408 BTC loaned and 17,852 pledged at 30 Sep 2026, against 9,377 loaned at 31 Dec 2025; less than 5% of holdings loaned or pledged after the post quarter repayment.
Long Ridge closingFERC approval 4 Nov 2026; $75.0m termination fee in some cases; up to about $900m of debt to assume; $785m bridge commitment.
Matagorda powerRights to up to 2,000 MW subject to the ERCOT Batch Zero study and the Texas audit ordered on 3 Aug 2026; up to $600m of milestone payments.
AI and HPC executionNo leases signed at 9 Nov 2026; Starwood predevelopment $17.7m incurred of $136.3m approved; Exaion's $79m contract is its first US customer.
Hosting roll offThird party hosting arrangements covering about 29% of energy capacity expire from Q3 2027 to Q1 2028; hosting contracts about $250.6m over the next 18 months.

How risk factors changed

  • Comparison: Item 1A of the 10-K FY2025 (filed 2 Mar 2026) against Item 1A of the 10-K FY2024 (filed 3 Mar 2025).
  • AI or HPC appears in 10 of 52 risk factors in FY2025 against 0 of 49 in FY2024.
  • Item 1A grew 24% to 12,176 words.
  • All eight added factors sit in the group on business risks and cover Starwood, Exaion, AI and HPC, bitcoin lending and forced liquidation.
  • The HODL wording was removed; MARA began selling bitcoin in 2H 2025 and extended sales to balance sheet holdings in 2026.
  • The 2026 Forms 10-Q added factors on Long Ridge, the Matagorda site and debt, incl. the $75.0m termination fee and the Texas data center audit of 3 Aug 2026.
Figure 10.1 Risk factors by change against the prior filing
Table 10.2 Size of the risk factor section
Measure10-K FY202410-K FY2025
Risk factors (count)4952
Words in Item 1A9,85212,176
Table 10.3 Risk factors added, removed and materially reworded
ChangeRisk factorWhat changed
AddedBitcoin lending and asset management credit and liquidity riskReplaces the narrower lending factor; states 9,377 BTC were loaned at 31 Dec 2025, a material portion of holdings, to counterparties that are not rated or investment grade.
AddedInability to liquidate or hedge bitcoin in market stressNew factor on exchange outages, thin order books, liquidations and auto deleveraging that could block bitcoin sales used to fund operating costs and capex.
AddedCompetition in mining and new marketsNew factor on competing for miners, low cost power and sites, and on entering AI and HPC against larger, better capitalized data center operators.
AddedStarwood Strategic Agreement execution and counterparty riskNew 640 word factor on the Feb 2026 Starwood agreement: triggers tied to a qualifying hyperscaler lease, a 24 month decision deadline, and forced sale of powered land if MARA declines to proceed.
AddedExaion acquisition and international operationsNew factor on the Feb 2026 purchase of France based Exaion from a state owned parent: French legal, tax, labor rules and possible postclosing challenges.
AddedAI and HPC may divert resources from miningNew factor that moving power to AI and HPC may limit deployed hashrate in a competitive mining market.
AddedAI and HPC expansion is capital intensiveNew factor that upfront data center capex may reduce liquidity and shift timing of cash inflows.
AddedAI and HPC strategy may not perform as plannedNew factor citing power timing, supply chain, labor, tariffs and specialized expertise as risks to expected long term high margin revenue.
RemovedBitcoin lending: borrower default and cyber threatsFolded into the broader new digital asset management factor.
RemovedProfessionalized mining may pressure bitcoin pricesFactor on miners selling to cover high operating costs dropped.
RemovedReliance on immersion cooling technologyFactor on immersion cooling at Granbury dropped.
RemovedReliance on third party hosting providersDropped; hosted sites still provided 537 MW and 29.2 EH/s at 31 Dec 2025 per Item 1.
RemovedRegulatory scrutiny of bitcoin holdings (AML, sanctions)Stand alone factor on regulators restricting transactions in bitcoin dropped.
RewordedBitcoin holdings: volatility and liquidity (formerly HODL strategy)Heading drops HODL strategy; text now covers selling bitcoin and cites convertible notes with put rights exercisable in 2027 that could require cash repurchases; body grew from 244 to 331 words.
RewordedMarket disruptions impair mining rigs; idlingRemoves the reference to late 2022 market disruptions; body similarity 0.79.
RewordedIntellectual property disputesAdds the May 2025 patent suit by Malikie Innovations, a patent assertion entity; body grew from 87 to 212 words.
RewordedIf bitcoin were deemed a securityRewritten: now states bitcoin is widely regarded as a commodity regulated by the CFTC and adds Investment Company Act risk; body cut from 366 to 262 words.
RewordedOperating in foreign jurisdictionsAdds Exaion, headquartered in France and formerly owned by a French state controlled entity, and EU political scrutiny.
RewordedTrading venue regulation gapsRephrased from 'unregulated nature and lack of transparency' to lack of a uniform framework; adds fraud and security failures affecting value of holdings.
RewordedTargeted energy or property regulation and taxesHeading adds property regulation; body grew from 124 to 218 words.
RewordedStock price volatilityExpanded list of drivers incl. bitcoin pricing and working capital financing; body grew from 115 to 223 words.
RewordedAt the market issuance dilutionMinor wording changes; still tied to ATM program.
RewordedSales of substantial sharesAdds sales after conversion of convertible securities and via ATM programs and Rule 144; body grew from 77 to 174 words.
Table 10.4 Risk factor updates in quarterly reports since the annual filing
FilingChange disclosed
10-Q Q1 2026 filed 11 May 2026Adds one factor: Long Ridge acquisition may not close; $75.0m termination fee if not closed by 30 Nov 2026 (extendable to 30 Jun 2027); $785m Barclays bridge; consent solicitation on 8.750% notes due 2032; plant 485 MW rising to 505 MW in 2H 2026.
10-Q Q2 2026 filed 6 Aug 2026Updates Long Ridge factor (505 MW now expected Q1 2027); adds factor on the Matagorda (HIF) acquisition with up to $600m consideration and ERCOT approval of 2,000 MW, citing the 3 Aug 2026 Texas audit order; adds factor on debt levels, noting debt secured by substantially all bitcoin holdings and margin call risk.
10-Q Q3 2026 filed 9 Nov 2026Long Ridge factor updated (505 MW expected 1H 2027, consent condition dropped after May 2026 consents); Matagorda factor recast around ERCOT Batch Zero study due 1H 2027 and the audit; debt factor now says MARA has incurred and may in the future incur bitcoin secured debt, after the $750m loans were repaid post quarter.

11 Stock Price, Scenarios & Sensitivity

  • MARA closed at $7.66 on 11 Nov 2026, 53.4% below the 52 week high of $16.43 and 34.6% above the low of $5.69 (5 Nov 2026, both intraday); month end close $11.33 in Sep 2026 and $6.77 in Oct 2026.
  • Valuation (computed): market value $2.97bn on 387.4m shares, 1.04 times bitcoin fair value of $2.84bn at 30 Sep 2026 and 1.26 times book value; enterprise value less bitcoin $2.23bn, 3.1 times TTM revenue. P/E is not meaningful after a TTM net loss of ($2.94bn).
  • Scenario basis: EV/sales, where enterprise value excludes bitcoin. Value per share in three years = (TTM revenue in Q3 2029 times the exit EV/sales multiple, plus cash and bitcoin less debt principal at 30 Sep 2026 of $741.3m) divided by shares. The sale of 13,597 BTC and the $750m loan repayment after 30 Sep 2026 leave that net figure about unchanged (computed). The growth rates and multiples are illustrative model assumptions.
Figure 11.1 MARA monthly closing price and three year scenarios

Critical factors and core assumptions

Table 11.1 Critical factors behind the best case
FactorCurrent valueBest case requiresEvidence in filings and calls
BTC price$83,556 at 30 Sep 2026; about $81,039 average sale price after 30 Sep 2026price above 2026 levels, lifting revenue and the value of bitcoin held37% lower average price of BTC mined cut Q3 2026 revenue by $94.8m (10-Q)
Lease signingsno leases signed; two targeted before end 2026several leases at Starwood joint venture sites8-K Ex 99.1, 9 Nov 2026
Long Ridge close and buildFERC approved 4 Nov 2026; closing pendingclosing by year end and up to 600 gross MW of AI load from mid 20288-K of 30 Apr 2026; 10-Q Q3 2026
Matagorda powerstudied load in ERCOT Batch Zero; Texas audit pendingallocation of up to 2,000 MW10-Q Q3 2026
Cost per BTC$39,674 purchased energy per BTC at owned sites; hosting covers about 29% of capacitylower cost per kWh as hosting arrangements expire from Q3 202710-Q Q3 2026
Convertible note puts$2.30bn principal; puts Jun 2027 ($291.6m) and Dec 2027 ($632.5m)puts met from cash without new shares10-Q debt note
  • Method: enterprise value less bitcoin to revenue (EV/sales). Starting point TTM Q3 2026 revenue $716.0m; today 3.1x (market value $2.97bn plus debt principal $3.05bn less cash $946.5m and bitcoin $2.84bn). Cash and bitcoin less debt ($741.3m) held at the 30 Sep 2026 level; the $80.4m redeemable noncontrolling interest is not deducted.
  • Best case: revenue +25% a year to $1.40bn as the bitcoin price recovers, Long Ridge adds power revenue and first leases start; exit 4.5x; share count +5%.
  • Base case: revenue +8% a year to $0.90bn with mining tracking the bitcoin price and network difficulty, Long Ridge power from 2027 and first lease revenue in mid 2028; exit 3.0x; share count +5%.
  • Worst case: revenue (15%) a year to $0.44bn after a lower bitcoin price and the Apr 2028 halving, no leases and no Matagorda power; exit 1.5x; share count +10% as 2027 puts are partly funded with equity.
  • Common to all cases: bitcoin mining remains the base load while HPC is developed; no dividend; the $500m buyback is not modelled.

Scenarios, three years forward

Table 11.2 Scenario analysis, TTM Q3 2026 to TTM Q3 2029
MeasureWorst caseBase caseBest case
Revenue CAGR, 3 years (%)(15.0)8.025.0
Revenue, TTM Q3 2029 ($bn)0.40.91.4
Exit EV/Sales (x)1.53.04.5
Implied price ($)3.298.4717.29
Change against $7.66 (%)(57)11126
Implied annual return (%)(24.6)3.431.2
Descriptionlower BTC price, halving, no leasesmining tracks BTC price; Long Ridge from 2027; leases from mid 2028BTC recovery, Long Ridge power and signed leases
Implied price = (revenue in TTM Q3 2029 times exit EV/sales plus $741.3m of cash and bitcoin less debt) divided by shares. Implied prices are rounded to whole dollars in this table: base $8.47, best $17.29, worst $3.29. All inputs are illustrative model assumptions.
Figure 11.2 Three year price scenarios

Sensitivity analysis

Table 11.3 Sensitivity of implied price to revenue CAGR and exit EV/Sales
Revenue CAGR \ EV/Sales1x2x3x4x5x
(15%)$2.90$3.98$5.07$6.15$7.23
(5%)$3.33$4.84$6.35$7.86$9.37
5%$3.86$5.90$7.94$9.97$12.01
15%$4.50$7.18$9.85$12.53$15.21
25%$5.26$8.70$12.14$15.57$19.01
Cells show implied share price in year 3. Share price on 11 Nov 2026 $7.66. Blue cells sit above it, red cells below. Rows: revenue CAGR over three years from TTM Q3 2026; columns: exit EV/sales with enterprise value excluding bitcoin; shares +5%.

Disclaimer

This analysis is for information only and is not financial advice. It is derived from public SEC filings retrieved via sec-api.io and is not a publication of the U.S. Securities and Exchange Commission. Scenario values are model outputs under stated assumptions and are not forecasts. Data as of 12 November 2026.

Sources

All company figures are read from SEC filings retrieved through the sec-api.io MCP server. Management statements are taken from the shareholder letters and releases filed as Exhibit 99.1; no earnings call transcript was used. Gross profit, capital expenditure, valuation ratios and scenario values are computed for this report from filed figures and the share price.

Table A.1 Filings used, with accession numbers
FormPeriodFiledAccession number
10-QQ3 20269 Nov 20260001507605-26-000028
8-K Ex 99.1Q3 20269 Nov 20260001507605-26-000026
10-QQ2 20266 Aug 20260001507605-26-000022
10-QQ1 202611 May 20260001507605-26-000016
10-KFY20252 Mar 20260001507605-26-000007
10-KFY20243 Mar 20250001507605-25-000003
10-K/AFY202324 May 20240001628280-24-025261
Table A.2 Forms 8-K of the last twelve months and other filings used
CompanyFormFiledAccession number
MARA Holdings8-K (Items 5.02, 9.01)25 Feb 20260001493152-26-008063
MARA Holdings8-K (Items 1.01, 7.01, 9.01)26 Feb 20260000950142-26-000532
MARA Holdings8-K (Items 2.02, 9.01)26 Feb 20260001507605-26-000004
MARA Holdings8-K (Items 8.01)26 Mar 20260000950142-26-000873
MARA Holdings8-K (Items 1.01, 7.01, 9.01)30 Apr 20260001193125-26-193982
MARA Holdings8-K (Items 2.02, 9.01)11 May 20260001507605-26-000014
MARA Holdings8-K (Items 5.02, 5.07, 9.01)22 Jun 20260001493152-26-029615
MARA Holdings8-K (Items 8.01, 9.01)25 Jun 20260000950142-26-001875
MARA Holdings8-K (Items 1.01, 2.01, 7.01, 9.01)9 Jul 20260000950142-26-002012
MARA Holdings8-K (Items 5.02, 7.01, 9.01)4 Aug 20260001493152-26-035933
MARA Holdings8-K (Items 2.02, 9.01)6 Aug 20260001507605-26-000020
MARA Holdings8-K (Items 1.01)25 Sep 20260000950142-26-002607
MARA Holdings8-K (Items 2.02, 9.01)9 Nov 20260001507605-26-000026
MARA Holdings10-Q Q1 20258 May 20250001507605-25-000009
MARA Holdings10-Q Q2 202529 Jul 20250001507605-25-000018
MARA Holdings10-Q Q3 20254 Nov 20250001507605-25-000028
MARA Holdings8-K Ex 99.1, Q3 2025 shareholder letter4 Nov 20250001507605-25-000026
Riot Platforms10-Q4 Nov 20260001104659-26-122417
CleanSpark10-Q6 Aug 20260001193125-26-338382
Cipher Digital10-Q2 Nov 20260001819989-26-000050
Core Scientific10-Q5 Nov 20260001839341-26-000030
IREN10-Q5 Nov 20260001878848-26-000066
Hut 810-Q4 Nov 20260001193125-26-446146
Strategy10-Q2 Nov 20260001050446-26-000060
Table B.1 Exhibits to Forms 8-K filed in the last twelve months
FiledExhibitDocumentContent
25 Feb 2026Ex 10.12026 form of RSU award agreement (2018 Equity Incentive Plan)RSUs vest in 11 equal quarterly installments from 1 Apr 2026 to 31 Dec 2028
25 Feb 2026Ex 10.22026 form of PSU award agreementPerformance metrics for FY2026: Economic Triad Megawatt Capacity and Annual Recurring Revenues; Payout up to 249% of target; relative TSR modifier over 2026 to 2028; total LTI payout capped at 200% of target
26 Feb 2026Ex 10.1Strategic Agreement with Starwood Capital Group Global IIICovers all MARA US mining sites except those in existing third party JVs; MARA elects 10% to 50% interest per JV; Starwood managing member
26 Feb 2026Ex 99.1Joint release of MARA and StarwoodJoint platform expected to support more than 1 GW of IT capacity initially, roadmap beyond 2.5 GW
26 Feb 2026Ex 99.1Q4 2025 shareholder letterQ4 2025 revenue $202.3m against $214.4m; FY2025 revenue $907.1m, up 38%; Q4 net loss $1.7bn ($4.52 per share) incl. $1.5bn fair value loss; FY net loss $1.3bn
26 Feb 2026Ex 99.2Q4 2025 results announcementAnnouncement of letter and conference call; no additional figures
30 Apr 2026Ex 10.1Equity Purchase Agreement for Long Ridge Energy & PowerBase price about $1.5bn with customary adjustments; sellers Ohio River Partners (FTAI Infrastructure); Termination right after 30 Nov 2026 (30 Jun 2027 if regulatory conditions pending); $75.0m termination fee payable by buyer in some cases
30 Apr 2026Ex 99.1Press release: agreement to acquire Long Ridge505 MW nameplate CCGT in Hannibal, Ohio (485 MW authorized), over 1,600 acres; Annualized adjusted EBITDA about $143.9m from 2H 2025 (Q3 2025 $35.7m, Q4 2025 $36.2m); all in operating cost below $15/MWh
11 May 2026Ex 99.1Q1 2026 shareholder letterRevenue $174.6m, down 18%; net loss $1.3bn ($3.31 per share); Energized hashrate 72.2 EH/s, up 33%; 2,247 BTC mined; sold 20,880 BTC at $70,137 average
11 May 2026Ex 99.2Q1 2026 results announcementresults announcement and call notice
22 Jun 2026Ex 10.1Third Amendment to 2018 Equity Incentive PlanAdds 18,000,000 shares to the plan, approved 18 Jun 2026 (83.7m for, 26.4m against)
25 Jun 2026Ex 99.1Long Ridge investor presentationFiled under Item 8.01 to give additional information on the Long Ridge transaction
9 Jul 2026Ex 99.1Press release: Matagorda County site (HIF) acquisitionProject Company holds land rights and a utility letter agreement for 2,000 MW; Up to $600m milestone payments; site to be developed with Starwood for HPC and flexible compute
4 Aug 2026Ex 99.1Press release: board appointmentsNancy Novak (former Chief Innovation Officer, Compass Datacenters) and Craig Hart (Avenue Capital, energy and power) appointed 1 Aug 2026; Replace Barbara Humpton and Georges Antoun, who resigned for personal reasons
6 Aug 2026Ex 99.1Q2 2026 shareholder letterRevenue $174.9m, down 27%; net loss $611.3m; adjusted EBITDA ($360.9m); Energized hashrate 70.3 EH/s, up 22%; 2,422 BTC mined; 700 blocks
6 Aug 2026Ex 99.2Q2 2026 results announcementresults announcement and call notice
9 Nov 2026Ex 99.1Q3 2026 shareholder letterRevenue $164.2m, down 35%; net income $632.1m ($1.28 per share); adjusted EBITDA $857.7m; 2,247 BTC mined; sold 3,891 BTC at $75,300; held 34,012 incl. 19,260 loaned or pledged
9 Nov 2026Ex 99.2Q3 2026 results announcementAnnouncement of letter and 9 Nov 2026 5:00 p.m. ET call; describes 1.9 GW today and path to about 4.8 GW